Joint Delivery Center Bernburg
Under the direction of LIST Bau Leipzig and with the support of LIST Ingenieure, a multi-carrier delivery hub (VZSP) was built for Deutsche Post AG in Bernburg. The building was constructed on a 10,200-square-meter lot in an industrial area surrounded by a solar farm.
All parties benefited from Deutsche Post AG’s long-standing partnership with the List Gruppe and the completion of numerous projects. For the newly founded company LIST Bau Leipzig, this provided the ideal framework for its first independently managed project. Workflows and processes were standardized during this period and contributed to efficiency during construction. The team was supported within the List Gruppe by LIST Bau Nordhorn and LIST Bau Holding. The project was handed over in May 2024 after only seven months of construction.